Geneva owns and operates its own electric utility, and we take great pride in providing reliable electric service to our residents and businesses. However, like all utilities, we are susceptible to outages caused by bad weather, animals, equipment issues and more. This blog is designed to provide updates on what caused outages after service has been restored. Large-scale incidents will be posted in real-time on the City's Alert Center on the our website homepage. Customers can subscribe to receive these updates via Notify Me.

Reporting Outages
Normal business hours
Public Works Electric Division at 630-2321503

After-hours, Weekends, Holidays
Police Department at 630-232-4736. FYI, our online request tracker system and social media accounts are not monitored 24 hours a day.

Sep 21

[ARCHIVED] Third Street Road Patching Update - Sept. 21

The original item was published from September 21, 2018 2:26 PM to July 1, 2019 12:00 AM

Third Street Road Patching
With clear weather in the forecast this week, the Third Street road patching project in downtown Geneva has gotten off to a good start.

After the road was closed between Campbell and Fulton streets early Sept. 17, construction crews began removing two sections of damaged concrete. Rebar was then set in place, and new concrete has been poured. The new surface needs seven days to cure before being reopened to traffic.

The last major component of the project is replacing the brick crosswalk at Franklin Street that also was damaged by heaving last winter.

All downtown businesses and sidewalks remain open during construction. Work is expected to be completed by Friday, Oct. 5. The City will provide another status update the week of Sept. 24.

For more information on the Third Street road patching project, including the detour route map, visit the City's website.