Following the concrete pouring Oct. 25, road construction crews are scheduled to begin paving the area near the South Street culvert crossing the week of Nov. 4, weather permitting.
Paving is tentatively set to take place Tuesday or Wednesday, Nov. 5 or 6. Crews will then groove the bridge deck Thursday, Nov. 7 and install the guardrail Friday, Nov. 8. The schedule is subject to change based upon weather and subcontractor schedules.
The City is anticipating the roadway will be reopened by Wednesday, Nov.
20, weather permitting. While the project will be substantially
completed, road striping and other ancillary work will still need to
take place.
South Street between Burgess Road and Southampton Drive has been closed since Aug. 9 for safety reasons after a sinkhole was discovered by the City. Engineering work took place during September, and demolition began Oct. 17.
For more information, including a detour route map, visit the