The original item was published from May 14, 2020 10:29 AM to August 1, 2020 12:00 AM

About 268 customers in the Geneva East subdivision and Geneva Business Park on the City's east side lost power at 7:32 a.m. May 14.
Commonwealth Edison's lines dropped service to the City's substation.