The original item was published from June 26, 2020 3:41 PM to July 30, 2020 12:00 AM
What's Ahead
The Illinois Department of Transportation announced the following operations will take place the week of June 29 with the State Street (Route 38) bridge resurfacing project:
- Clean off the bridge deck and place the overlay surface.
Background & More Info
Two lanes of traffic, one in each direction, will remain open throughout
construction of the bridge that spans the Fox River in downtown Geneva.
The project will be done in two phases with work starting in the
outside lanes and then later shifting to the interior lanes.
Work began in late May and is anticipated to be completed in August, weather permitting.
Check back on the blog for project updates. For more information, visit the
State Street bridge construction web page on the City’s website.