Geneva's 2022 street improvement program kicks off in late July with saw cutting and removing sidewalks on Viking Drive, Kaneville Road and Pioneer Court.
The tentative schedule, which is weather dependent and subject to change, for the next several weeks includes:
Friday, July 29
Sidewalk and curb saw cutting begins on Viking Drive from Fabyan Parkway working towards Kaneville Road.
Aug. 1-5
Monday-Tuesday
Continue saw cutting and removing sidewalk and curb concrete on Viking Drive. Operations will transition to Kaneville Road.
Wednesday-Thursday
Kaneville Road sidewalk and curb removal continues. Crews start framing and pouring new concrete on Viking Drive.
Friday
Crews finish removing sidewalk/curbs on Kaneville Road and proceed to Pioneer Court. Concrete pouring continues on Viking Drive and starts on Kaneville Road
Aug. 8-12
With sidewalk/curb removal completed, crews will keep framing and pouring new concrete on Kanevlle Road and Pioneer Court.
Aug. 15-19
Crews begin to clean up sidewalk/curb sites on all three roadways, and landscape work begins later in the week.
The City is working with Geneva Construction to develop a schedule for the 14 road resurfacing and drainage projects that are included in the 2022 street improvement program, which is expected to be completed in October.
Residents looking to get more details on the upcoming construction are invited to an informational meeting at 6 p.m. Wednesday, Aug. 3 at the Geneva Public Works Department, 1800 South St. Public Works staff will provide an overview of the construction activity and be available to answer questions. The public can enter the building through the east side door.
People can subscribe to receive road work updates via “Notify Me” on the City’s website. For more information about the street improvement program, contact the City’s Civil Engineer Elton Orozco at 630-232-1279 or via email.