Geneva owns and operates its own electric utility, and we take great pride in providing reliable electric service to our residents and businesses. However, like all utilities, we are susceptible to outages caused by bad weather, animals, equipment issues and more. This blog is designed to provide updates on what caused outages after service has been restored. Large-scale incidents will be posted in real-time on the City's Alert Center on the our website homepage. Customers can subscribe to receive these updates via Notify Me.

Reporting Outages
Normal business hours
Public Works Electric Division at 630-2321503

After-hours, Weekends, Holidays
Police Department at 630-232-4736. FYI, our online request tracker system and social media accounts are not monitored 24 hours a day.

Jul 09

[ARCHIVED] Underground Electric Replacement Project - July 9 Update

The original item was published from July 9, 2024 11:55 AM to August 1, 2024 12:00 AM

The City began an underground electric replacement project in March 2024 along Geneva Drive and South Third Street. Replacing underground utility cables enhances our electric service reliability in Geneva.

July 9 Update

Meade Electric, the City contractor, began working on Third Street the week of July 8 starting near the Union Pacific-West train tracks. Crews will be pulling electric cable through manholes from 8 a.m. to 3 p.m. Wednesday and Thursday, July 10-11, on the southeast corner of Third and South streets.

The project will require closing the eastbound South Street traffic lane at the Third Street intersection. The westbound South Street lane will remain open. Downtown patrons can use Second Street to access businesses and parking lots on South Street east of Third Street.

The sidewalk on the southeast corner of Third/South intersection will be shut down during construction, but access to local businesses will not be impacted. Work on the sidewalk only could extend into Friday, July 12.

The schedule is subject to change due to inclement weather.

Once work is finished near South Street, operations will shift north on Third Street to Fulton, Franklin, Campbell and James streets during July and August. All lanes of traffic will remain open on Third Street, but parking spaces and sections of sidewalk may be temporarily closed at various times. Construction will not occur in the days leading up to the Geneva Arts Fair on Saturday and Sunday, July 27-28.

Work on Geneva Drive has been substantially completed. 

Subscribe For Updates

People can subscribe to receive future Pardon The Progress blog updates via “Notify Me” on the City website. For more project information, visit the Underground Electric Replacement web page.