The original item was published from November 7, 2024 4:09 PM to March 1, 2025 12:00 AM

Union Pacific is building a third railroad line near the current UP-West railway tracks spanning from Peck Road in Geneva to West Chicago. Operations started in 2022, and the overall project is expected to be completed in spring 2025.
Nov. 7 Update
The construction contractor is now anticipating the Western Avenue railroad crossing will be reopened to motorists by Friday, Nov. 15, weather permitting. Crews still need to pour concrete and finish asphalt resurfacing in the area in the coming days.
The Fox River Trail just south of Island Park will continue to be closed to the public through Nov. 15 to accommodate construction operations. That section of trail along the east bank of the Fox River was shut down on Nov. 4. The Fox River Trail is closed to northbound, southbound and feeder trail traffic. Trail patrons should adhere to signage where posted and plan for alternative routes.
The Route 31 overflow parking lot south of the underpass could possibly be reopened by Thanksgiving.
The Third Street commuter permit parking lot on the southwest side of the tracks is scheduled to be completed by the end of 2024.
All schedules are subject to change due to weather or construction delays.
Subscribe For Updates
People can subscribe to receive future Pardon The Progress blog updates via “Notify Me” on the City website. For more project information, visit the Third Main Line construction web page.
While the City of Geneva is providing information to the community, the City has no authority or control over the Union Pacific project. The details shared by the City are only as good as the information provided to us by Union Pacific.