[ARCHIVED] Geneva Street Program - Sept. 4 Update

City Road Construction

The City's contractor, Geneva Construction, will be working on eight road resurfacing and drainage projects as part of the Geneva 2024 street program. Work began in mid-August and is expected to be completed in November, weather permitting. A map and project locations can be found online.

Sept. 4 Update

The contractor is scheduled to pour concrete for the eastern curb on East Side Drive Wednesday and Thursday, Sept. 4-5. Once that is finished, construction operations will then shift over to replacing the sidewalk and curbs on the western side of East Side Drive. Road resurfacing will occur following the completion of the concrete work.

With sidewalk work finished on Westfield Course, landscape restoration will begin Sept. 5. Residents should expect asphalt milling, which will generate additional truck traffic, to get underway Friday, Sept. 6 on Westfield Course.

Construction crews also will be applying road striping Sept. 5 in various sections of Geneva.

All road construction is weather-permitting and subject to change.

Subscribe For Updates

People can subscribe to receive road work updates via Notify Me on the City’s website. For more information about the street program, contact the City’s Civil Engineer Elton Orozco at 630-232-1279 or via email.

Facebook Twitter Email

Other News in Road Construction

East State Street Reconstruction

East State Street Reconstruction - March 6 Update

Posted on: March 6, 2026 | Last Modified on: March 6, 2026
East State Street Reconstruction

East State Street Reconstruction - Feb. 27 Update

Posted on: February 27, 2026 | Last Modified on: February 27, 2026
East State Street Reconstruction

East State Street Reconstruction - Feb. 13 Update

Posted on: February 13, 2026 | Last Modified on: February 13, 2026