The City's contractor, Geneva Construction, will be working on eight road resurfacing and drainage projects as part of the Geneva 2024 street program. Work began in mid-August and is expected to be completed in November, weather permitting. A map and project locations can be found online.
Sept. 13 Update
The east sidewalk on East Side Drive is being reopened to the public Sept. 13. Construction crews also were expected to finish up landscaping work on the east side of the street.
Starting on Monday, Sept. 16, the east side sidewalk will be the recommended pathway of travel for parents and students to Harrison Street School. The contractor is planning to begin removing both the sidewalk and curb on the western side of East Side Drive the week of Sept. 16.
All road construction is weather-permitting and subject to change.