The City's contractor will be working on eight road resurfacing and drainage projects as part of the Geneva 2024 street program. A map and project locations can be found online.
Aug. 8 Update
Pre-construction activity got underway this week with the contractor starting to remove concrete as part of the sidewalk replacement near Geneva High School. Crews also began similar operations along East Side Drive, including removing the curb. East Side Drive will be resurfaced from State (Route 38) to Division streets this year.
The City expects to start underground/storm sewer construction Monday, Aug. 12 in the area of Scott Boulevard and Maple Court. Drainage work also will get underway near West Street Pond.
All road construction is weather-permitting and subject to change.
Subscribe For Updates
People can subscribe to receive road work updates via Notify Me on the City’s website. For more information about the street program, contact the City’s Civil Engineer Elton Orozco at 630-232-1279 or via email.